試卷年份2011年上半年
試題題型【單選題】
試題內(nèi)容

You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as ( ) .
A、Ahead of schedule
B、Behind schedule
C、On schedule
D、Having not enough information provided