密查电影在线观看完整版|行尸走肉第7季在线观看免费完整版|欧美区日韩区|五月婷婷深爱五月,一级不卡免费视频 ,色戎 同类电影大尺度未删减版,国产色宗合

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A seller is awarded a contract to build a pipeline. The contract terms and conditions require that a work plan be issued for the buyer's approval prior to commencing work, but the seller fails to provide one. Which of the following is the BEST thing for the buyer's project manager to do?
A、File a letter of intent.
B、Develop the work plan and issue it to the seller to move things along.
C、Issue a default letter.
D、Issue a stop work order to the seller until a work plan is prepared.


相關試題

推薦文章
合作網(wǎng)站內(nèi)容