密查电影在线观看完整版|行尸走肉第7季在线观看免费完整版|欧美区日韩区|五月婷婷深爱五月,一级不卡免费视频 ,色戎 同类电影大尺度未删减版,国产色宗合

軟題庫 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the planning phase, the project manager estimates task durations based on the availability of the resources. How should the project manager gain commitment from the resources’ providers?
A、 Share the project management plan and human resource management plan to the functional manager.
B、 Send an e-mail to the staffing department with a completed resource request.
C、 Involve the functional managers in developing the plan and obtain their approval.
D、 Assure the functional managers that the resources will be released and completed.


相關(guān)試題

推薦文章