試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the first year, a project experiences a significant amount of issues. At beginning of the second year, the project stabilizes, diminishing dramatically the number of issues. What should the project manager do ?
A、Cancel the remaining scheduled risk assessment sessions.
B、Diminish the amount of management reserve.
C、Continue identifying new risks and reassessing existing risks.
D、Perform a qualitative risk analysis of the residual risks.